I saw it coming and told them this in written comments - December 2002:

1. An airport is a very long-life development whose siting, design, and environmental mitigation strategy should provide for
many years into the future. Active airfields in this region date from the early 1940’s, already 60 years old and with indefinite
remaining life. It is appropriate to plan a permanent facility with at least 100 years of service life.

2. The physical scope of the project to be assessed should include: the airport fully built out (two parallel runways, one
crosswind runway, passenger terminal sized to accommodate the passenger traffic implied by two parallel runways, fuel,
cargo and general aviation facilities sized for full build-out, on-site and off-site stormwater treatment structures sized for full
build-out) and any cumulative impacts triggered by the presence of a hub airport (on-airport industries, off-airport industrial
and distribution facilities, commercial facilities, residential developments, roads, streets, utility corridors, and related
stormwater treatment structures). If the scope is reduced, the Airport Layout Plan (ALP) showing the ultimate planned buildout
should be permanently reduced accordingly, to assure that the environmental design is compatible with the ultimate
planned build-out. All the stormwater mitigation structures may not need to be built to ultimate capacity in the first phase, but
the environmental analysis should establish the requirements for building to full capacity.

3. Analysis of the ambient environment should follow the best science available, based on field observations in addition to
archived data, because the archived data is understood to be incomplete in the project area.

4. Seasonal studies of fresh water quality and flow from the site to West Bay should be done, and should cover an interval long
enough to recognize effects of the prolonged drought now in progress.

5. The design of the airport-plus-cumulative-impacts stormwater runoff treatment structures should produce effluent with
quality equal to or better than the ambient fresh water observed in the seasonal studies per Item (4.)

6. Construction should be phased and scheduled to avoid exposing more bare earth than the
stormwater runoff control structures and methods in place can treat to pre-construction
ambient water quality.

7. Temporary construction facilities such as mobile offices, employee parking, mobilization
and material laydown/storage areas should be designed and operated to treat stormwater
runoff to pre-construction ambient water quality.

8. In any event, including hurricane rainfall conditions, silt transport to Burnt Mill Creek and/or Crooked Creek and their tributaries in excess of pre-construction ambient conditions,
including hurricane rainfall conditions, should not occur during construction.

The permits say the same thing, but little effort was made to comply during construction until the lid blew off in April 2009.